A screw should be inspected on the bench, against a written list, before it is ever fitted. Case depth, hardness, straightness, the flights and the thread. Then take the baseline on the machine, because a drift in melt pressure six months later means nothing without the reading you recorded on day one.
Commissioning is the acceptance test. A free test on 10-20 kg of your material runs before the balance is paid, and if the run misses the agreed output by more than 5% the deposit is refundable. The handover report then carries the measured baseline, the written routine and the running hours, so later faults can be judged against a reference.
The handover routine, step by step
- Measure case depth, hardness and straightness on the bench before the screw is fitted.
- Record the four-hour output and the specific energy as your machine baseline.
- Teach the 20-minute screen change every 3-4 hours as a discipline, not a suggestion.
- Fines above 0.5% and a slow climb in output are the first-week signals.

The bench check before it goes in
A screw should be inspected on the bench against a written checklist before it is fitted. The checks are not difficult: case depth, surface hardness, straightness, and the condition of the flights and the thread. What is difficult is doing them without a written list, because nobody opens a new screw box expecting to find a defect. The plastic pellets glossary on this site is a fair place to agree what the terms mean before the conversation starts.
The figures to hold against are published. The nitrided case is 0.5-0.7 mm at HV 900-1000 in this plant, with published supplier specifications running 0.5-0.8 mm case, HV 900-1,000, Ra 0.4 and 0.015-0.02 mm straightness. Core hardness should be around HB 240-280. Measure, photograph, and write the readings down against the screw number, and put them in the quality control file where the next person can find them.
Size and geometry belong to the same check. Screws up to 4 m long and 220 mm in diameter are turned and milled in house, so the drawing for your machine should match the part in the crate. Confirm that the screw will pass into the barrel bore, that the drive end coupling matches, and that the bore itself is free of set-in material.
What the inspection is really for

Inspection is not mainly about catching a bad part, although that does happen. It is about establishing a baseline, so that six months later, when the melt pressure drifts, you have a reference to compare against. Without a starting measurement you are arguing from memory, and memory at the end of a long shift on a shop floor is not reliable.
Take the baseline on the machine rather than on the bench where you can. Record the melt temperature profile, the output measured over four hours on finished bagged pellets, and the specific energy, which on these lines runs 0.26-0.50 kWh/kg. Specific energy is the number that moves first when a screw and barrel start to lose their geometry.
Record the contamination you are actually running, not the contamination you hope to run. The published figures are about 2% non-melting contamination tolerated by a single screw at 60-80 mesh, and 5-8% by a two stage line at 100 mesh. Above 8%, the honest conclusion is that washing belongs in the budget before another screw is ordered, and that is a decision about the plastic recycling machine as a whole.
Commissioning day
The commissioning run is the acceptance test, and it is run on your material, not on ours. A free test on 10-20 kg of the buyer’s material is carried out before the balance is paid, and the video, the measured output, the specific energy and the pellet photos are sent over. If the test run misses the agreed output by more than 5%, the deposit is refundable.
That 5% is measured against a stated figure, so agree the number in writing before the machine ships. Output is quoted as finished bagged pellets averaged over four hours rather than as a peak hourly rate, and the four-hour average is the honest basis for a plant that runs continuously. Specify the mesh, the pellet size and the material, and let the run settle before anyone reads the figure.
On site, installation takes 7-10 days for a line and 3-5 days for a single machine, including commissioning and two days of operator training. Those training days are where the screening routine has to be taught properly, because the 20-minute screen change every 3-4 hours is a discipline, and a discipline taught badly returns as unplanned stops in the first month.
The first week of running
Most faults appear in the first week, and most of them are process faults rather than mechanical ones. The common one is a melt quality problem caused by a feed that has changed, and the second is contamination arriving after a washing step that was not set up for the material now in front of it. When the size reduction equipment upstream has been re-ordered for a different grade, that change shows up here first. Log the first week’s material against the first week’s output.
Watch startup, because it is where a tired wear pair shows up first. A cold start takes 25-40 minutes and a restart from a 120 °C standby takes 10 minutes. A plant that cannot reach a stable melt inside that window is usually fighting a barrel or screw problem, and it will appear in the pellet photos as oval or misshapen pellets and in the output figure as a slow climb.
Then watch the fines, because fines are the earliest honest indicator of wear or over-shear. 0.5% is normal and 2% is a maintenance signal, and the first thing to do is tighten the screen change interval. Cutting the interval costs 20 minutes. A worn screw costs a delivery.
The handover report
The handover report is the document that closes the job, and it should carry the baseline numbers from the inspection and the commissioning run: case depth and hardness measured, straightness, the four-hour output, the specific energy, the pellet photographs, the screen mesh, and the running hours the machine was commissioned at. Then both sides can tell later whether the wear is normal.
It should also carry the routine in writing. Screen change every 3-4 hours, blade check every 8 hours, the spare screw, the die plate and the two screen packs that keep unplanned stops under 2%, and the fact that wear parts are stocked for three years. Written routines survive the operator who invented them, which is the only kind worth writing down.
Keep the file with the machine. In every application, the question that comes back months later is not about the machine but about the wear part: which case depth, which alloy, and what the baseline reading was. The FAQ pages are a fair starting point for the routine, but they cannot know your baseline, and your applications describe the duty better than any specification sheet. Send that file to the people who will run it.
Handover checklist and the figures to record
The inspection routine only works if the same measurements are taken every time. The table is the check sheet, with the reading that triggers each action.
| Item | Acceptance figure | Where it is recorded |
|---|---|---|
| Case depth | 0.5-0.7 mm nitrided | Inspection sheet, at the bench |
| Surface hardness | HV 900-1000 | Inspection sheet, measured |
| Straightness | 0.03 mm in house | Inspection sheet, before fitting |
| Commissioning run | 10-20 kg of buyer material | Video and test report |
| Output baseline | Bagged pellets over four hours | Test report, with photos |
| Specific energy | 0.26-0.50 kWh/kg | Test report, against baseline |
| Screen interval | Change every 3-4 hours | Handover report, in writing |
Questions buyers ask about this machine
Q1: What should be on the screw handover report?
The measured case depth and hardness, the straightness, the four-hour output on finished bagged pellets, the specific energy, the pellet photographs, the screen mesh and the running hours the machine was commissioned at. Without those baseline figures, later wear claims become arguments from memory.
Q2: How is screw hardness confirmed before the machine ships?
Ask for the case depth and the hardness in writing, then measure the part on arrival. Published figures are HV 900-1,000 over a 0.5-0.8 mm case, with a bimetallic layer at 2.0-3.0 mm and HRC 58-62. A hardness figure that was never measured on the screw is a claim, not a fact.
Q3: What output should I expect in the acceptance test?
Output is quoted as finished bagged pellets averaged over four hours, and the test runs 10-20 kg of the buyer’s own material. If the run misses the agreed output by more than 5%, the deposit is refundable, which is why the material you send matters more than the nameplate on the machine.
Q4: What should I check weekly to keep the screw alive?
Screen changes every 3-4 hours, an 8-hourly blade check, and a written record of output and specific energy at a fixed interval each shift. Fines above the 0.5% normal level are the early signal, and 2% means the melt is being over-sheared and the wear part needs examining.
Also worth reading: plastic recycling machine.
Three more notes from the same test floor: Extruder Screw and Barrel: What the Part Does, Nitrided vs Bimetallic Extruder Screw: Which to Buy, Extruder Screw Diameter and Length: How to Match It and Screw and Barrel Cost: Replacement and Total Cost.
About the author
Zhou Gong (周工) builds recycling lines at TENGLONG Plastic Machinery, a factory in Linyi, Shandong, with 18,000 m² of floor area, 30-plus staff and 820-plus lines delivered to 46 export markets. I ask for the baseline readings in writing before a line ships, because a dispute six months later turns on a number that was never recorded. The numbers in this article come from test runs and from dated published sources, not from a sales sheet.
If you want a recommendation rather than a catalogue, send the material form, the contamination level and the target output. We return a model and a price range within one working day, and the test run on 10-20 kg of your own material is free before the balance is paid.