The only supplier test worth running is a trial on your own material, with your own feedstock, at the throughput you intend to buy. A video of somebody else’s agricultural film running through a clean machine tells you that the machine works; it tells you nothing about your material, and that is the only thing your quotation is about.
Ask for four numbers in writing before you pay the balance: measured output in kg/h, specific energy in kWh/kg, the pellet or chunk size with its tolerance, and the measured bulk density of the product. If the deposit is at risk until those numbers match the quotation, the supplier’s incentive and yours are the same.
What to insist on before the balance is paid
- A free test on 10–20 kg of your material, with measured output, specific energy and photographs sent before the balance is paid.
- If the test run misses the agreed output by more than 5%, the deposit should be refundable. That clause is the whole test.
- Standard terms here are 30% deposit and 70% before shipment, with L/C at sight above US$50,000; anything beyond that needs a reason.
- The warranty runs 18 months from commissioning or 24 months from shipment, and wear parts are stocked for three years.

Insist on a trial with your own material
The single most useful thing you can do before signing is send material to the factory and ask for it to be run. Not a sample of their material — your material.
We run this for our own buyers free of charge and they pay the freight. The buyer gets a video of the test run, the measured output, the specific energy in kWh per kilogram, and photographs of the resulting chunks. That is a low-cost test for the buyer and a decisive one, because a supplier who will not run your material on their machine is telling you something about the delivery.
Send 10–20 kg. Enough to fill a batch, not enough to be a production trial. And send the worst material you actually process, not the cleanest — a test on clean film proves the machine works, and only a test on your worst film proves it works for you.
The numbers to get in writing

Several of these have to be written into the contract rather than assumed, because each one is a place where a dispute can otherwise happen.
Throughput, defined as finished output. Not extruder throughput, not the feed rate the machine was designed for. We quote finished, bagged material averaged over four hours, which is 3–6% below extruder throughput. Specify the basis and the number has a meaning.
Specific energy in kWh/kg. Our lines run 0.26–0.50 kWh/kg depending on polymer and moisture. On a 500 kg/h line running 6,000 hours a year, a 0.05 kWh/kg difference is 150,000 kWh — usually more than the entire price gap between a cheap machine and a good one.
Bulk density of the output. State a minimum. A machine that produces the right tonnage at the wrong density has not solved your feeding problem.
The screen and blade specification, the motor and inverter makes, and the electrical configuration matched to your actual supply voltage — standard is 380 V / 50 Hz three-phase, and we also build 415 V / 50 Hz, 440 V / 60 Hz and 220 V single-phase for the smallest mill. IE3 motors and IP54 panels throughout.
Payment terms that keep you in control
Our terms are 30% T/T deposit with the order and 70% before shipment against photographs and video of the test run. L/C at sight is accepted for orders above US$50,000. We do not ask for full prepayment, and we do not ship against a promise.
The 70% is paid against evidence, not against intent. Photographs and video of your material running on the machine, before the machine leaves the factory. That sequence protects both sides: you are not paying for steel in a container, and the supplier has not shipped a machine that does not work.
The clause worth adding to the contract is the performance condition: if the test run misses the agreed output by more than 5%, the deposit is refundable. That is our standard, and any supplier who refuses to write it is telling you the output figure in the quotation is not a commitment.
Warranty, spares and what happens after commissioning
The warranty is 18 months from commissioning or 24 months from shipment, whichever comes first, covering parts and labour for manufacturing defects. Wear parts — knives, screens, heater bands, seals — are excluded, but we stock them for three years, and that three-year commitment is worth more to a running plant than the warranty itself.
For the installation itself: seven to ten days on site for a full line, three to five days for a single machine, including commissioning, two days of operator training and a signed handover report. Travel and accommodation are covered by the buyer.
Then ask the question most buyers skip: who answers the phone at month eight when the machine is running badly? A supplier with a test hall, a spare parts warehouse and an engineering team that has run production lines answers it. A trading company answers it with a forwarding email.
What to write into the purchase agreement
These are the clauses that decide what happens if the machine disappoints, and they are the ones worth negotiating hardest.
| Item | Specify | Why |
|---|---|---|
| Throughput | Finished output in kg/h, averaged over 4 hours | Removes the screw-versus-finished ambiguity |
| Energy | Specific energy in kWh/kg on your material | The largest operating cost over five years |
| Output quality | Minimum bulk density and chunk form | Defines whether the densification actually worked |
| Electrical | Voltage, frequency, motor and panel specification | Standard is 380 V / 50 Hz; IE3 motors, IP54 panels |
| Payment | 30% deposit, 70% against test-run evidence | You pay for demonstrated output, not steel in a container |
| Performance | Deposit refundable if output misses by more than 5% | Makes the quoted number a commitment |
| Warranty | 18 months from commissioning or 24 months from shipment | Wear parts excluded but stocked for three years |
Frequently asked questions
Q1: Can I see the machine running before I pay the balance?
Yes, and that is standard practice here. We send a video of the four-hour test run with your material, the PLC trend, pellet or chunk sample photos and the test report, and only then is the balance due. If the result misses the agreed output by more than 5%, the deposit is refundable.
Q2: What should a material trial actually demonstrate?
Four things: the measured finished output per hour, the specific energy in kWh per kilogram, photographs of the chunk or pellet sample, and a machinery fault rate over the run. A supplier who shows you a speedometer reading instead of those four numbers has shown you nothing that can be verified.
Q3: How much should I pay up front?
30% deposit with the order and 70% before shipment against photographs and video of the test run is our standard. L/C at sight is accepted above US$50,000. Full prepayment before the machine has run on your material is the arrangement to decline.
Q4: What if the delivered machine underperforms the quotation?
That is exactly what the performance clause is for. If the test run misses the agreed output by more than 5%, the deposit is refundable. We would rather refund a deposit than ship something that fails in month three — which is also why we turn down projects that only work at the lowest price.
Also worth reading: the 12-platform comparison and FAQ with 33 answered questions.
Three more notes from the same test floor: Plastic Agglomerator Machine: What It Does and Its Limits, How to Size a Plastic Agglomerator Machine for Film Scrap, Plastic Agglomerator Maintenance: Knife Clearance and Uptime and Plastic Agglomerator in a Film Recycling Line: Layout.
About the author
Zhou Gong (周工) builds recycling lines at TENGLONG Plastic Machinery, a factory in Linyi, Shandong, with 18,000 m² of floor area, 30-plus staff and 820-plus lines delivered to 46 export markets. I would rather lose a trial than ship a machine that misses its number: the cost of a disputed machine is far higher than the cost of a refused deposit. The numbers in this article come from test runs and from dated published sources, not from a sales sheet.
If you want a recommendation rather than a catalogue, send the material form, the contamination level and the target output. We return a model and a price range within one working day, and the test run on 10–20 kg of your own material is free before the balance is paid.