A Granules Line That Grows from 500 to 3,000 kg/h

Modular layout lets a 500 kg/h start reach 3,000 kg/h on the same footprint. Which stages carry the expansion and what to reserve on day one.

The TL-GPL uses a modular layout so a 500 kg/h start can grow to 3,000 kg/h without rebuilding the plant. Washing and drying are usually the first constraints: 500 kg/h has two tanks and a two-stage dryer, while the largest model has three tanks, ultrasonic cleaning and a three-stage dryer.

The expansion only works if floor area, transformer capacity, water permits and buffer silo capacity were reserved on day one. Buffer between washing and pelletizing is what lets the two sections run at different rates while one stage is serviced.

Designing for the second phase

  • Reserve floor space toward the final 58 by 12 m envelope.
  • Size incoming power for the eventual 900 kW load.
  • Washing and drying usually become the first bottleneck.
  • Buffer silos let sections expand without stopping the whole line.
3D render of an orange and yellow TENGLONG extruder with a top hopper and a control cabinet
3D render of an orange and yellow TENGLONG extruder with a top hopper and a control cabinet. Used here as a visual reference for a line laid out to add capacity later. Rendering, not a photograph of a customer plant.

Buy for today, reserve for tomorrow

A recycling business rarely knows its final tonnage at the moment it orders its first line. The TL-GPL is laid out as a modular system so a 500 kg/h start can grow to 3,000 kg/h without rebuilding the plant. That claim is only useful if the reserved space and services are identified at the beginning.

The modular layout is physical: stages are separate units connected by conveying, with buffer capacity between them. Adding capacity means adding a parallel stage or a larger module where the original design left room, not replacing the whole line.

The commercial advantage is that the first investment is smaller than the eventual plant. A business can prove the market at 500 kg/h and expand when the orders exist, rather than financing unused capacity for years.

Which stages carry the expansion

Rendered factory floor with a green TENGLONG granulator, a hopper and an operator at the control panel
Rendered factory floor with a green TENGLONG granulator, a hopper and an operator at the control panel. Shown here as production context. Rendering, not a photograph of a customer plant.

Washing is usually the first constraint. The TL-GPL-500 has two wash tanks, while the 1500 and 3000 models have three and the largest adds ultrasonic cleaning. Reserve floor area around the washing section if a second tank is likely.

Dewatering and drying follow washing. The 500 model uses a press and two-stage dryer; the larger models use three stages. A dryer that is sized only for today’s moisture load will become the bottleneck when throughput rises.

Pelletizing is comparatively easy to add as a parallel module, because the line offers water ring or strand cutting matched to the polymer. A second extruder fed from the same dried-flake buffer is a natural expansion step.

What to reserve on day one

Reserve floor area in the direction the material flows. The 500 model occupies 32 by 8 m and the 3000 model 58 by 12 m, so the site should be chosen with the larger envelope in mind even if only the first stage is installed.

Reserve power capacity at the transformer. A 280 kW line can grow to a 520 kW and eventually a 900 kW line; sizing the incoming supply for the final stage avoids a second electrical project.

Reserve water supply and discharge capacity using the same logic. Make-up water at 0.8 to 1.2 cubic metres per tonne scales with output, and a permit obtained for the final tonnage is easier than one revisited later.

The buffer is the key component

Buffer silos between washing and pelletizing allow the two sections to run at different rates for short periods. That is what makes an expansion possible without stopping the whole line when one stage is serviced.

Buffer capacity also absorbs variation in the incoming feedstock. A wetter batch of film takes longer to dry, and a buffer keeps the extruder fed while the drying stage catches up.

The central MCC with per-stage logging becomes more valuable as the line grows. With more stages running, fault tracing without stage-level data becomes slow and uncertain.

Planning the expansion contract

Ask the supplier to state which parts of the line are expandable and which are not. A modular claim is meaningful only when the interfaces, reserved space and future module prices are written down.

Include the future configuration in the quotation discussion even if it is not ordered. A supplier who has sized the site for the eventual line will design the first line differently from one who has not.

Our turnkey page and twelve-platform comparison describe the range and the dimensional envelope of each model. Send the intended final tonnage with the first enquiry so the layout can be planned for it.

Expansion path by stage

A line can be bought for today’s tonnage and built for tomorrow’s. The table shows which stages carry the expansion.

Stage 500 kg/h Growth path Reserve
Washing 2 tanks 3 tanks, ultrasonic option Floor beside tanks
Drying Press + 2-stage Press + 3-stage Height and footprint
Pelletizing One module Parallel extruder Buffer silo capacity
Power 280 kW installed Up to 900 kW Transformer and MCC
Water 0.8-1.2 m3/t Scales with output Supply and discharge permit

Frequently asked questions

Q1: Can a 500 kg/h line really grow to 3,000 kg/h?

Yes. The TL-GPL uses a modular layout, so a smaller start can be expanded on the same site. The practical conditions are that floor space, power, water and buffer capacity were reserved when the first line was installed.

Q2: Which stage becomes the bottleneck first?

Usually washing, then drying. The 500 model has two wash tanks and a two-stage dryer, while larger models use three tanks and a three-stage dryer. Reserve space around those stages.

Q3: How should I size the transformer for future expansion?

Plan for the final configuration. Installed load rises from 280 kW to 520 kW and then 900 kW, with the transformer at 1.25 times installed load. Sizing for today’s line means a second electrical project later.

Q4: Why is a buffer silo important for expansion?

It lets washing and pelletizing run at different rates for short periods and absorbs variation in feedstock moisture. With a buffer, a second pelletizing module can be added without stopping the washing section.

Also worth reading: plastic granules production line, twelve-platform comparison and factory testing.

Three more notes from the same test floor: What a Turnkey Granules Line Actually Includes, 90 C Friction Washing: What Each Stage Removes, Water Use in a Granules Line: 0.8 to 1.2 m3 per Tonne and 280 to 900 kW: Power Planning for a Turnkey Line.

About the author

Zhou Gong (周工) is a recycling machinery engineer at TENGLONG Plastic Machinery in Linyi, Shandong, where 30-plus staff work across 18,000 m² and 12 machine platforms covering 100 to 3,000 kg/h. Tell me the final tonnage even if you are ordering the smallest line. It changes the first drawing. Every figure used here has been measured on a machine or taken from a dated published source, not from a brochure.

Send the material form, the contamination level and your target output to our engineering team and you get a model and a price range within one working day. A test run on 10–20 kg of your own material is free, and if the measured output misses the agreed figure by more than 5%, the deposit is refundable.