CE marked · ISO 9001:2015 · 18-month warranty

· FAQ · By

Strand Pelletizing Line: How Much Floor Space to Plan

Floor length follows bath length, and access space is part of the envelope. Measured dimensions for three strand lines and how to plan a second one.

A strand pelletizing line occupies 8.5 m at 250 kg/h, 10.5 m at 500 kg/h and 12.5 m at 800 kg/h, measured from the die face to the bagging station. Add about a metre for bag access and the extruder footprint at the front. Bath length drives the number because 4, 5 and 6 m baths are process requirements.

If that length is unavailable, the answer is a different cutting method rather than a shorter bath. A water ring pelletizer uses about 40% less floor space and an underwater pelletizer removes the bath entirely, but both give up the visible melt path that makes a strand line easy to judge by eye.

Planning the real envelope

  • Footprints are 8.5, 10.5 and 12.5 m from the die face to the bagging point.
  • Add a metre at the discharge end for bag access.
  • Allow clear space along the machine for screw and knife work.
  • Reserve utilities now if a second line is likely within two years.
3D render of a long white TENGLONG granulating line with several linked machine units arranged in a row
3D render of a long white TENGLONG granulating line with several linked machine units arranged in a row. Used here as a visual reference for the floor envelope of a strand line. Rendering, not a photograph of a customer plant.

The number that is always missing

Most enquiries arrive with a throughput and a floor area, and the floor area is usually the extruder footprint. A strand pelletizing line adds a bath, an air knife, a cutter and a bagging point downstream of the die. The published footprint figures are measured from the die face to the bagging station, and they are larger than buyers expect.

The TL-ST-200 needs 8.5 m by 1.2 m at 150 to 250 kg/h. The TL-ST-400 needs 10.5 m by 1.4 m at 350 to 500 kg/h. The TL-ST-800 needs 12.5 m by 1.6 m at 600 to 800 kg/h. Add roughly one metre at the end for bag access, and add the extruder footprint at the front.

Those numbers are for the strand section alone. A complete line also needs the force feeder or crusher upstream, a blower or conveyor to the bagger, and clear space around the control cabinet. The auxiliary equipment page on our site sets out the conveyors, silos and cutters that sit around the main machine.

Bath length drives the envelope

Rendered booth scene with a red TENGLONG machine and visitors talking at the stand
Rendered booth scene with a red TENGLONG machine and visitors talking at the stand. Shown here as production context. Rendering, not a photograph of a customer plant.

The reason the line grows is the bath. A 4 m bath suits 150 to 250 kg/h, a 5 m bath suits 350 to 500 kg/h, and 800 kg/h needs 6 m or the core stays soft at the cutter. Bath length is a process requirement, not a design preference, so it cannot be shortened to fit a smaller room.

If floor length is genuinely unavailable, the answer is a different cutting method. A water ring pelletizer cuts at the die face and needs about 40% less floor space than a strand line. An underwater pelletizer removes the bath entirely. Both give up the visible melt path that makes a strand line easy to judge by eye.

The choice is therefore not between a long and a short machine. It is between a line that shows the melt and a line that fits the building. Make that trade explicitly at the quotation stage, because changing cutting method after installation means replacing the whole downstream section.

Access space is part of the footprint

A line drawn as a rectangle on a plan will be installed by people who need to stand somewhere. The screw pull, the die cleaning and the bed knife change all require access along the machine. For a twin-screw line we quote a screw extraction interval that assumes clear space along the barrel; the same principle applies to a strand cutter.

Allow clearance at the feed end for the conveyor, and around the control cabinet for the electrician. A cabinet that cannot be opened fully is a cabinet that will be serviced badly. Heights matter too: the TL-ST lines stand between 1.5 m and 1.8 m tall, and a line with a silo needs more headroom.

The bagging point deserves specific attention. Pellets arrive continuously, and someone has to change bags. If the bagger sits against a wall, that job happens in a cramped corner and takes longer than it should. One metre of clear space at the discharge end is a small price for a shift that runs smoothly.

Where the line fits next to an extruder

The strand line starts at the die face, so the extruder position sets everything. Place the extruder so the strands fall into the bath at a shallow angle and the bath runs in a straight line to the cutter. A bend in the strand path adds guide rolls and adds break points.

Water and power have to reach the bath and the cutter. The bath pump is 2.2 kW on the TL-ST and the cutter motor ranges from 5.5 to 15 kW. A chiller, if fitted, needs its own space and a drain. These services are easy to forget when the plan shows only the machine outline.

Our twelve-platform comparison lists the footprint of every machine in the range, which helps when deciding whether a strand line or a different platform fits a specific building. A turnkey line solves the same problem at a larger scale by matching every stage to one layout.

Planning for a second line

If a second line is likely within two years, leave the space now. Utility connections installed during the first build cost less than a second construction phase, and a shared compressor or water loop is sized once rather than twice.

The TL-GPL turnkey platform is designed for this: a 500 kg/h start can grow to 3,000 kg/h on the same footprint because the stages are modular. A strand line is less flexible, but the same logic applies to the services around it.

Send the actual floor drawing, including columns and door swings, when asking for a quotation. A drawing produces a useful answer about layout; a square metre figure produces only a guess. Our engineering team returns a model and a dimensional check within one working day when the floor plan is attached.

Measured envelopes of the three strand models

Floor length follows output because the bath follows output. These are the measured envelope figures from the three published models.

Model Output Bath Footprint Height
TL-ST-200 150-250 kg/h 4 m 8.5 x 1.2 m 1.5 m
TL-ST-400 350-500 kg/h 5 m 10.5 x 1.4 m 1.6 m
TL-ST-800 600-800 kg/h 6 m 12.5 x 1.6 m 1.8 m
Add at discharge Bag access – About 1 m –

Frequently asked questions

Q1: How much floor does a strand pelletizing line need?

From the die face to the bagging station, 8.5 m at 250 kg/h, 10.5 m at 500 kg/h and 12.5 m at 800 kg/h. Add about a metre for bag access and the extruder footprint at the front.

Q2: Can I shorten the bath to fit my building?

No, not without changing the process. Bath length follows output: 4, 5 and 6 m for the three models. A shorter bath leaves the strand core soft and the cutter smears instead of cutting.

Q3: What is the alternative if I lack floor length?

A water ring pelletizer cuts at the die face and uses about 40% less floor space than a strand line. An underwater pelletizer removes the bath altogether. Both give up the visible melt path of a strand line.

Q4: What services does the strand section need?

The bath pump is 2.2 kW and the cutter motor runs from 5.5 to 15 kW. A chiller, if specified, needs space and a drain. Allow clear access along the machine for screw and knife work and around the control cabinet.

Also worth reading: twelve-platform comparison.

Three more notes from the same test floor: Why Cubic Pellets Still Win in Injection Feeding, Strand Bath Length and Water Temperature Explained, Strand Breaking at the Die: From Symptom to Cause and Strand Cutter Maintenance: Knife Clearance and Blades.

About the author

Zhou Gong (周工) builds recycling lines at TENGLONG Plastic Machinery, a factory in Linyi, Shandong, with 18,000 m² of floor area, 30-plus staff and 820-plus lines delivered to 46 export markets. Send me the floor drawing with the columns and door swings. A square metre figure produces a guess; a drawing produces a layout. The numbers in this article come from test runs and from dated published sources, not from a sales sheet.

If you want a recommendation rather than a catalogue, send the material form, the contamination level and the target output. We return a model and a price range within one working day, and the test run on 10–20 kg of your own material is free before the balance is paid.

Related reading