A pellet silo is a modest line item next to the pelletizer, but the price differences are not where buyers expect them. Installed vessel capacity runs from US$14,000–32,000 for 50–100 m³ to US$400,000–900,000 for a 2,000 m³-plus silo farm, and the rate per cubic metre falls as the vessel grows.
Discharge and instrumentation move the total more than the shell does: a gravity discharge with a rotary valve is US$8,000–18,000, an aeration and feeder package US$35,000–70,000, and a full monitoring package US$12,000–28,000. Coatings, instrumentation, freight and erection add their own percentage on top of all that.
Where the money actually goes
- Vessel cost per m³ falls with scale, from US$280–400 down to US$180–250 on a large silo farm.
- Discharge is the big variable: US$8,000–18,000 for gravity, US$35,000–70,000 for aeration and a feeder.
- Coatings add 8–12%, instrumentation 5–10% and freight and erection another 8–15% of project value.
- Running cost is US$4,000–8,000 a year, and bag handling loses 0.3 to 1.0% of the product on top.

What the Vessel Costs
A pellet silo is not expensive in absolute terms, but it is not a small number either. Published figures for installed vessel capacity: 50–100 m³ at US$14,000–32,000, which works out at US$280–400 per m³; 200–500 m³ at US$55,000–150,000, or US$250–330 per m³; 800–1,200 m³ at US$170,000–330,000, or US$200–280 per m³; and 2,000 m³-plus silo farms at US$400,000–900,000, or US$180–250 per m³.
The trend in those numbers is the useful part. The cost per cubic metre falls as the vessel grows, so a plant planning a second phase pays a better rate for volume it has already planned for. It also means the cheapest silo on any given list is the small one, and the small one is the one that has to be doubled later, when the bagging hall has been built around it.
Published prices are indicative starting prices for 2026 and configuration-dependent, so the number on a website is a starting point for a conversation, not a quotation. Before you request a quotation, work out the configuration line by line: for a silo it is the material, the flow pattern, the discharge method and the instrumentation. Those four answers move the price more than the vessel diameter does.
Discharge and Instrumentation

Discharge is the first place the money goes beyond the shell. Gravity discharge with a rotary valve comes in at US$8,000–18,000. Fluidised aeration pads, a bin activator and a screw feeder together run US$35,000–70,000, which is several times the cost of the valve and, for difficult material, the only version that works reliably.
Instrumentation is the second. Basic level indication is US$1,200–3,500, and a full monitoring package is US$12,000–28,000. Between those two figures sit the things a plant with a night shift actually wants: continuous level, high level alarm, temperature in the vessel, and an output that can be read from the control room instead of climbed up to look at.
These two packages are the ones worth arguing about, because the vessel shell price is broadly predictable across suppliers while the discharge and instrumentation packages are where two quotations can differ by more than the shell. Ask for both packages priced as separate lines on the quotation, then decide which of them your material and your shift pattern actually require.
Coatings, Freight and Erection
Installed cost runs roughly US$250–600 per m³ depending on scale, and that figure is the vessel before the items that turn a delivery into a working installation. Coatings add 8–12% of project value, instrumentation adds 5–10%, and freight and erection add another 8–15%. Those are the published add-ons, and they are where a budget written from the vessel price alone stops matching the invoice.
The shell itself has two build choices with real money in them. Bolted silos run 10–20% cheaper installed, fit in a 40 ft container and take 2–3 weeks to assemble instead of 6–8. Hot-dip galvanizing adds 15–25% to the shell cost but moves service life from 12–15 years to 25–30 years, which is a straightforward trade between paying now and paying later.
Put these in the same line of the budget: freight, foundations, water treatment, a first spare-parts stock and installation are all quoted separately from the machine price. A silo that arrives and cannot be founded, because the foundation was never in the civil package, has wasted its delivery slot. For a plant buying plastic recycling equipment as a package, the foundation and erection package is the item most often left out of the first quotation and found in the second.
Running Cost and the Bags
A silo costs US$4,000 to US$8,000 a year to inspect, maintain and run. Against a pelletizing line that is small, but it is not nothing, and it covers the inspection of the internals, the level instrumentation and the dust handling that keeps the fines out of the product.
The bigger running number is downstream of the silo, in the bagging operation. Supersacks cost US$6 to US$14 each plus US$15 to US$40 a tonne in labour, liner and pallet expense. Those figures belong to the bagging station rather than to the vessel, but a silo is the reason the bagging station can be fed steadily enough to keep the labour cost down.
The loss that nobody budgets for is product. Bag handling loses 0.3 to 1.0% of the product. On a plant moving a few thousand tonnes a year that is a real quantity of pellets, and the silo influences how much is lost, because a steady level at the discharge and a clean bag change are what keep the handling gentle.
The Payback Case
Published payback above 1,000 tonnes a year is 18 to 36 months, and that figure belongs in the same conversation as the price of the vessel. An unplanned extruder stop is costed at US$5,000–50,000 per hour depending on line size, so the buffer that prevents one hour of that cost pays for itself in a way a lower vessel price never does.
There is a second payback inside the same project, and it belongs to the flow decision rather than to the vessel. A mass-flow cone adds roughly 15 to 20% to the fabricated shell cost but removes the need for manual rathole breaking, which costs four to eight labour hours per incident at US$85 an hour. Put those two figures next to each other and the premium looks less like a cost and more like an insurance premium.
Scale the silo against the line it serves and the argument closes. A turnkey plastic granules line is quoted at US$85,000 and a PET pelletizing line at US$120,000, so a vessel in the tens of thousands is a modest item in the whole product range. The plant that loses money is not the one that paid too much for the vessel; it is the one that stopped the line for four hours because the vessel was full and nobody had asked for a level switch.
Where a pellet silo project budget actually goes
A silo is quoted per cubic metre, but the bill arrives as a vessel, a discharge system and an installation. The table separates the three.
| Item | Published figure | Note |
|---|---|---|
| Vessel, 50–100 m³ | US$14,000–32,000 | US$280–400 per m³ |
| Vessel, 200–500 m³ | US$55,000–150,000 | US$250–330 per m³ |
| Vessel, 800–1,200 m³ | US$170,000–330,000 | US$200–280 per m³ |
| Silo farm, 2,000 m³ and above | US$400,000–900,000 | US$180–250 per m³ |
| Gravity discharge with rotary valve | US$8,000–18,000 | The simple route |
| Aeration pads, bin activator, screw feeder | US$35,000–70,000 | For material that will not flow |
| Basic level indication | US$1,200–3,500 | Enough for a single shift |
| Full monitoring package | US$12,000–28,000 | Level, alarm and readback |
| Coatings, instrumentation, freight and erection | 8–12%, 5–10%, 8–15% of project value | Published add-ons |
| Annual running cost | US$4,000–8,000 | Inspection, maintenance and running |
Questions buyers ask about this machine
Q1: How much does a pellet storage silo cost?
Published figures for installed vessel capacity: 50–100 m³ at US$14,000–32,000, 200–500 m³ at US$55,000–150,000, 800–1,200 m³ at US$170,000–330,000, and 2,000 m³-plus silo farms at US$400,000–900,000.
Q2: How much does discharge equipment add to the price?
A gravity discharge with a rotary valve comes in at US$8,000–18,000. Fluidised aeration pads, a bin activator and a screw feeder together run US$35,000–70,000, which is the price of making difficult material flow reliably.
Q3: What is the installed cost per cubic metre?
Roughly US$250–600 per m³ depending on scale, before the add-ons: coatings at 8–12% of project value, instrumentation at 5–10% and freight and erection at another 8–15%.
Q4: How long does a silo take to pay back?
Typical payback above 1,000 tonnes a year is 18 to 36 months. An unplanned extruder stop is costed at US$5,000–50,000 per hour depending on line size, and that exposure is what the buffer is bought against.
Read next, if the same model is going on your line: Pellet Storage Silo: What It Does on a Pelletizing Line, Mass Flow vs Funnel Flow in a Pellet Storage Silo, How Big Should Your Pellet Storage Silo Be and Silo Commissioning: Level, Discharge and Acceptance.
About the author
Zhou Gong (周工) is a machinery engineer at TENGLONG Plastic Machinery, a 30-plus staff factory in Linyi, Shandong with 18,000 m² of floor space, 12 machine platforms and 820-plus installed lines. I read quotations for a living, and the silo line is the one most often written as a single number when it should be five. Where a number appears in this article it was taken from a test run or from a source with a date on it, and a figure we could not check has been left out entirely.
Ask for a recommendation rather than a quotation and we will work from your material, your contamination level and your target output. A model and a price range follow within one working day, the test on 10-20 kg of your material is free, and a result more than 5% below the agreed output leaves the deposit refundable.